50 labourers can dig a pond in 16 days. How many labourers will be required to dig another pond, double in size in 20 days?
उत्तर
In 16 days for diging pond labour reqd.
In 1 day, labour reqd. = 50 × 16
In 20 days, labour reqd. = `(50xx16)/20`
In 20 days, with double work, labour reqd.
`=(50xx16xx2)/20`
= 5 × 8 × 2
= 80
Hence labourers required = 80
APPEARS IN
संबंधित प्रश्न
4 men or 6 women earn Rs. 360 in one day. Find, how much will:
(i) a man earn in one day?
(ii) a woman earn in one day?
(iii) 6 men and 4 women earn in one day?
A family of 5 persons can be maintained for 20 days with Rs.2,480. Find, how long Rs.6944 maintains a family of 8 persons?
Ten men, working for 6 days of 10 hours each, finish `5/21` of a piece of work. How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 days?
The price of 25 identical articles is ₹1,750. Find the price of one article
If the cost of a dozen soaps is ₹ 460.80, what will the cost of 3 dozen soaps?
Weight of 15 books is 6 kg. What is the weight of 45 such books?
The temperature dropped 18 degree Celsius in the last 24 days. If the rate of temperature drop remains the same, how many degrees will the temperature drop in the next 18 days?
Mr. Chopra pays ₹ 12,000 as rent for 3 months. How much does he has to pay for a year if the rent per month remains same?
A truck requires 108 litres of diesel for covering a distance of 1188 km. How much diesel will be required by the truck to cover a distance of 3300 km?
If a deposit of ₹ 2,000 earns an interest of ₹ 500 in 3 years, how much interest would a deposit of ₹ 36,000 earn in 3 years with the same rate of simple interest?