A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________ - Mathematics

Advertisements
Advertisements

प्रश्न

A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________

रिक्त स्थान भरें

उत्तर

A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ₹ 1,20,000 

shaalaa.com
Compound Variation
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 4: Life Mathematics - Exercise 4.4 [पृष्ठ १५०]

APPEARS IN

सामाचीर कलवी Mathematics [English] Class 8 TN Board
अध्याय 4 Life Mathematics
Exercise 4.4 | Q 1. (v) | पृष्ठ १५०

संबंधित प्रश्न

A can finish a job in 3 days whereas B finishes it in 6 days. The time taken to complete the job working together is __________ days


A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days


210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?


A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?


A soap factory produces 9600 soaps in 6 days working 15 hours a day. In how many days will it produce 14400 soaps working 3 more hours a day?


A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?


A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?


Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?


If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?


Amutha can weave a saree in 18 days. Anjali is twice as good a weaver as Amutha. If both of them weave together, then in how many days can they complete weaving the saree?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×