प्रश्न

A can do a work in 6 days and B in 9 days. How many days wlll both take together to complete the work?

विकल्प

  • 7.5 days

  • 5.4 days

  • 3.6 days

  • 3 days

MCQ

उत्तर

3.6 days

Explanation:

  A B  
D → 6 9 → `18/5` = 3.6 days
E → 3 : 2  