A group of workers accepted to do a piece of work in 25 days. If 6 of them did not turn up for the work and the remaining workers did the work in 40 days, then the original number of workers was
विकल्प
22.
18.
20.
16.
MCQ
उत्तर
16.
Explanation:
Let x no. of men can do work in 25 days
ATQ using M1D1 = M2D2
25x = (x – 6) 40
15x = 240
x = 16