प्रश्न
From the given elements of operational plan in Column-I and the objectives given in Column-II, choose the correct pair:
Column I | Column II |
(a) Routing | i) comparing materials, product or performance with established standards. |
(b) Dispatching | ii) determining the exact path a product/service has to follow, right from raw material to finished good. |
(c) Inspection | iii) initiating production as per the pre-conceived production plan. |
(d) Follow-up | iv) expediting function that relates to evaluation and appraisal of work performed. |
विकल्प
(a) – (i)
(b) – (ii)
(c) – (iii)
(d) – (iv)
MCQ
जोड़ियाँ मिलाइएँ
उत्तर
(d) – (iv)