If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days? - Mathematics

Advertisements
Advertisements

प्रश्न

If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

विकल्प

  • 52

  • 31

  • 13

  • 65

MCQ
योग

उत्तर

52
Number of men required to finish the work in 26 days = 40

Number of men required to finish it in 1 day = 40 × 26 = 1040 men (More men means less days)

Number of men required to finish it in 20 days = `1040/20` = 52.