Advertisements
Advertisements
प्रश्न
In a call center, 6 employees working for 10 hours complete a certain task. They started working at 11:00 a.m. This continued till 5.00 pm and after that, for each hour one more employee is added till the work gets completed. At what time will they complete the work?
विकल्प
7: 10 pm
8: 00 pm
7: 35 pm
6:35 pm
MCQ
उत्तर
8: 00 pm
Explanation:
M1D1 = M2D2
MD = M1D1 + M2D2 .........MnDn
6 × 10 = 6 × 6 + 7x1 + 8x1 +.........
60 − 36 = 7 + 8 +........... nth hour
24 = 7 + 8 + 9
i.e. 3 hr more
∴ 8 PM
shaalaa.com
Time and Work (Entrance Exam)
क्या इस प्रश्न या उत्तर में कोई त्रुटि है?