प्रश्न

In a call center, 6 employees working for 10 hours complete a certain task. They started working at 11:00 a.m. This continued till 5.00 pm and after that, for each hour one more employee is added till the work gets completed. At what time will they complete the work?

विकल्प

  • 7: 10 pm

  • 8: 00 pm

  • 7: 35 pm

  • 6:35 pm

MCQ

उत्तर

8: 00 pm

Explanation:

M1D1 = M2D2

MD = M1D1 + M2D2 .........MnDn

6 × 10 = 6 × 6 + 7x1 + 8x1 +.........

60 − 36 = 7 + 8 +........... nth hour

24 = 7 + 8 + 9

i.e. 3 hr more

∴ 8 PM