हिंदी

In the modification of a plant layout of a factory four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A, B, C, D and E available. Because of limi - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

In the modification of a plant layout of a factory four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A, B, C, D and E available. Because of limited space, machine M2 cannot be placed at C and M3 cannot be placed at A. The cost of locating a machine at a place (in hundred rupees) is as follows.

Machines Location
A B C D E
M1 9 11 15 10 11
M2 12 9 10 9
M3 11 14 11 7
M4 14 8 12 7 8

Find the optimal assignment schedule.

सारिणी
योग

उत्तर

Here, number of rows and columns are not equal.

∴ The problem is unbalanced.

∴ It is balanced by introducing dummy job machine M5 with zero cost.

Also, M2 cannot be placed at C and M3 cannot be placed at A.

Let a very high cost (`oo`) be assigned to corresponding elements.

∴ Matrix obtained is as follows:

Machines Location
A B C D E
M1 9 11 15 10 11
M2 12 9 `oo` 10 9
M3 `oo` 11 14 11 7
M4 14 8 12 7 8
M5 0 0 0 0 0

Step 2: Row minimum 

Subtract the smallest element in each row from every element in its row.

The matrix obtained is given below:

Machines Location
A B C D E
M1 0 2 6 1 2
M2 3 0 `oo` 1 0
M3 `oo` 4 7 4 0
M4 7 1 5 0 1
M5 0 0 0 0 0

Step 3: Column minimu

Here, each column contains element zero.

∴ Matrix obtained by column minimum is same as above matrix.

Step 4: Draw minimum number of vertical and horizontal lines to cover all zeros.

First cover all rows and columns which have maximum number of zeros.

Machines Location
A B C D E
M1 `cancel(0)` `cancel(2)` `cancel(6)` `cancel(1)` `cancel(2)`
M2 `cancel(3)` `cancel(0)` `cancel(oo)`  `cancel(1)` `cancel(0)`
M3 `oo` 4 7 4 `cancel(0)`
M4 `cancel(7)` `cancel(1)` `cancel(5)` `cancel(0)` `cancel(1)`
M5 `cancel(0)` `cancel(0)` `cancel(0)` `cancel(0)` `cancel(0)`

Step 5: From step 4, minimum number of lines covering all the zeros are 5, which is equal to order of the matrix i.e., 5

∴ Select a row with exactly one zero, enclose that zero in () and cross out all zeros in its respective column.

Similarly, examine each row and column and mark the assignment ().

∴ The matrix obtained is as follows:

Machines Location
A B C D E
M1 0 2 6 1 2
M2 3 0 `oo` 1 `cancel(0)`
M3 `oo` 4 7 4 0
M4 7 1 5 0 1
M5 `cancel(0)` `cancel(0)` 0 `cancel(0)` `cancel(0)`

Step 6: The matrix obtained in step 5 contains exactly one assignment for each row and column.

∴ Optimal assignment schedule is as follows:

Machines Location Cost
(in hundred rupees)
M1 A 9
M2 B 9
M3 E 7
M4 D 7
M5 C 0

The total minimum cost (in hundred rupees) = 9 + 9 + 7 + 7 + 0 = 32.

shaalaa.com
Special Cases of Assignment Problem
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 7: Assignment Problem and Sequencing - Exercise 7.1 [पृष्ठ ११९]

APPEARS IN

बालभारती Mathematics and Statistics 2 (Commerce) [English] 12 Standard HSC Maharashtra State Board
अध्याय 7 Assignment Problem and Sequencing
Exercise 7.1 | Q 6 | पृष्ठ ११९

संबंधित प्रश्न

Four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A, B, C, D and E available. Because of limited space, machine M2 cannot be placed at C and M3 cannot be placed at A. The cost matrix is given below.

Machines Places
  A B C D E
M1 4 6 10 5 6
M2 7 4 5 4
M3 6 9 6 2
M4 9 3 7 2 3

Find the optimal assignment schedule


Fill in the blank :

An assignment problem is said to be unbalanced when _______.


Maximization assignment problem is transformed to minimization problem by subtracting each entry in the table from the _______ value in the table.


Fill in the blank :

In an assignment problem, a solution having _______ total cost is an optimum solution.


To convert the assignment problem into a maximization problem, the smallest element in the matrix is deducted from all other elements.


State whether the following is True or False :

The purpose of dummy row or column in an assignment problem is to obtain balance between total number of activities and total number of resources.


State whether the following is True or False

In number of lines (horizontal on vertical) > order of matrix then we get optimal solution.


Solve the following problem :

Solve the following assignment problem to maximize sales:

Salesman Territories
I II III IV V
A 11 16 18 15 15
B 7 19 11 13 17
C 9 6 14 14 7
D 13 12 17 11 13

Solve the following problem :

The estimated sales (tons) per month in four different cities by five different managers are given below:

Manager Cities
P Q R S
I 34 36 33 35
II 33 35 31 33
III 37 39 35 35
IV 36 36 34 34
V 35 36 35 33

Find out the assignment of managers to cities in order to maximize sales.


Choose the correct alternative:

The cost matrix of an unbalanced assignment problem is not a ______


An unbalanced assignment problems can be balanced by adding dummy rows or columns with ______ cost


A ______ assignment problem does not allow some worker(s) to be assign to some job(s)


State whether the following statement is True or False:

To convert the assignment problem into maximization problem, the smallest element in the matrix is to deducted from all other elements


Find the assignments of salesman to various district which will yield maximum profit

Salesman District
1 2 3 4
A 16 10 12 11
B 12 13 15 15
C 15 15 11 14
D 13 14 14 15

For the following assignment problem minimize total man hours:

Subordinates Required hours for task
I II III IV
A 7 25 26 10
B 12 27 3 25
C 37 18 17 14
D 18 25 23 9

Subtract the `square` element of each `square` from every element of that `square`

Subordinates Required hours for task
I II III IV
A 0 18 19 3
B 9 24 0 22
C 23 4 3 0
D 9 16 14 0

Subtract the smallest element in each column from `square` of that column.

Subordinates Required hours for task
I II III IV
A `square` `square` 19 `square`
B `square` `square` 0 `square`
C `square` `square` 3 `square`
D `square` `square` 14 `square`

The lines covering all zeros is `square` to the order of matrix `square`

The assignment is made as follows:

Subordinates Required hours for task
I II III IV
A 0 14 19 3
B 9 20 0 22
C 23 0 3 0
D 9 12 14 0

Optimum solution is shown as follows:

A → `square, square` → III, C → `square, square` → IV

Minimum hours required is `square` hours


To solve the problem of maximization objective, all the elements in the matrix are subtracted from the largest element in the matrix.


Three new machines M1, M2, M3 are to be installed in a machine shop. There are four vacant places A, B, C, D. Due to limited space, machine M2 can not be placed at B. The cost matrix (in hundred rupees) is as follows:

Machines Places
  A B C D
M1 13 10 12 11
M2 15 - 13 20
M3 5 7 10 6

Determine the optimum assignment schedule and find the minimum cost.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×