Solve the following question and mark the best possible option.
It takes 8 people working at equal rates to finish work in 96 days. How long will 6 workers take to finish the same work?
विकल्प
92 days
128 days
111 days
84 days
MCQ
उत्तर
128 days
Explanation:
Required number of days = 96 x `8/6` = 128 days.