State whether the given statement is of inverse variation.
Number of workers on a job and time taken by them to complete the job.
उत्तर
As the number of workers increases, the time taken by them to finish a job decreases. This is a statement of the inverse.
संबंधित प्रश्न
State whether the given statement is of inverse variation.
Number of pipes of same size to fill a tank and the time taken by them to fill the tank.
State whether the given statement is of inverse variation.
Petrol filled in the tank of a vehical and its cost
State whether the given statement is of inverse variation.
Area of circle and its radius.
A car with speed 60 km/hr takes 8 hours to travel some distance. What should be the increase in the speed if the same distance is to be covered in 7\[\frac{1}{2}\] hours?
120 bags of half litre milk can be filled by a machine within 3 minutes find the time to fill such 1800 bags?
If 15 workers can build a wall in 48 hours, how many workers will be required to do the same work in 30 hours?