Ten men take 4 days to complete the task of tarring a road. How many days would 8 men take?
उत्तर
Number of men | Number of days |
10 | 4 |
8 | x |
More the men lesser the number of days required to finish the work.
So, the number of men and the number of days required to complete the work are inversely proportional to each other.
`10/8 = "x"/4`
`=> "x" = (10 xx 4)/8`
⇒ x = 5
Thus, when 8 men are involved so, 5 days will be required.
APPEARS IN
संबंधित प्रश्न
A machine in a soft drink factory fills 840 bottles in six hours. How many bottles will it fill in five hours?
Rohit bought 12 registers for Rs 156, find the cost of 7 such registers.
A and B can finish a work in 20 days. A alone can do \[\frac{1}{5}\] th of the work in 12 days. In how many days can B alone do it?
A and B can do a piece of work in 6 days and 4 days respectively. A started the work; worked at it for 2 days and then was joined by B. Find the total time taken to complete the work.
A birthday party is arranged in third floor of a hotel. 120 people take 8 trips in a lift to go to the party hall. If 12 trips were made how many people would have attended the party?
An auto rickshaw takes 3 hours to cover a distance of 36 km. If its speed is increased by 4 km/h, the time taken by it to cover the same distance is ______.
If 45 persons can complete a work in 20 days, then the time taken by 75 persons will be ______ hours.
From the following table, determine if x and y are in direct proportion or not.
x | 1 | 4 | 9 | 20 |
y | 1.5 | 6 | 13.5 | 30 |
Shabnam takes 20 minutes to reach her school if she goes at a speed of 6 km/h. If she wants to reach school in 24 minutes, what should be her speed?
Here is a keyboard of a harmonium: What is the ratio of black keys to all keys on the given keyboard.