Twenty-five workers were employed to complete a compound wall in 12 days. Five workers left after working for 4 days. The remaining 20 workers completed the work. In how many days the total job was -

Advertisements
Advertisements

प्रश्न

Twenty-five workers were employed to complete a compound wall in 12 days. Five workers left after working for 4 days. The remaining 20 workers completed the work. In how many days the total job was completed?

विकल्प

  • 15 days

  • 16 days

  • 14 days

  • 18 days

MCQ

उत्तर

14 days

Explanation:

25 worker complete work in 12 days then ATQ

25 × 12 = 25 × 4 + 20 × x

25 (12− 4) = 20 x

`(25xx8)/20="x"`

x = 10

Total work completed in 10 + 4 = 14 days