Advertisements
Advertisements
प्रश्न
8 men can finish half of the work in 3 days. If the remaining work is to be completed in 2 days. then the no. of additional men required are?
पर्याय
4
5
7
9
MCQ
उत्तर
4
Explanation:
8 men will take 3 days to do the half work.
Now, `1/2` work (remaining} is to be completed in 2 days.
Hence 8 × 3 = n × 2 ⇒ n = 12
So, 4 additional men are required.
shaalaa.com
Time and Work (Entrance Exam)
या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?