Advertisements
Advertisements
प्रश्न
A and B can do a piece of work in 12 days, while B and C can do it in 15 days where as A and C can do it in 20 days. How long would each take to do the same work?
उत्तर
(A + B) complete the work in 12 days.
∴ (A + B)’s 1 day work = `1/12` ...(1)
(B + C) complete the work in 15 days
∴ (B + C)’s 1 day work = `1/15` ...(2)
(A + C) complete the work in 20 days
∴ (A + C)’s 1 day work = `1/20` ...(3)
Now (1) + (2) + (3) =
[(A + B) + (B + C) + (A + C)]’s 1 day work = `1/12 + 1/15 + 1/20`
(2A + 2B + 2C)’s 1 day work = `5/60 + 4/60 + 3/60`
2(A + B + C)’s 1 day work = `(5 + 4 + 3)/60`
5 | 12, 15, 20 |
4 | 12, 3, 4 |
3 | 3, 3, 1 |
1, 1, 1 |
L.C.M = 5 × 4 × 3 = 60
(A + B + C)’s 1 day work = `12/(60 xx 2)`
(A + B + C)’s 1 day work = `1/10`
Now A’s 1 day’s work = (A + B + C)’s 1 day work – (B + C)’s 1 day work
= `1/10 - 1/15`
= `3/30 - 2/30`
= `1/30`
∴ A takes 30 days to complete the work.
B’s 1 day work – (A + B + C)’s 1 day’s work – (A + C)’s 1 day’s work
= `1/10 - 1/20`
= `6/60 - 3/60`
= `(6 - 3)/60`
= `3/60`
= `1/20`
B takes 20 days to complete the work.
C’s 1 day work (A + B + C)’s 1 day work – (A + B)’s 1 day work
= `1/10 - 1/12`
= `6/60 - 5/60`
= `(6 - 5)/60`
= `1/60`
∴ C takes 60 days to complete the work.
APPEARS IN
संबंधित प्रश्न
A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days
A alone can do a piece of work in 35 days. If B is 40% more efficient than A, then B will finish the work in ___________ days
A alone can do a work in 10 days and B alone in 15 days. They undertook the work for ₹ 200000. The amount that A will get is ________
A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?
If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?
A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?
Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?
A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together
A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together
If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?