A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?
उत्तर
Let the number of men to be appointed more be x.
Motor pumps | Days | Employees | |
Planned | 540 | 150 | 40 |
Produced | 180 | 75 | 40 |
Remaining | 360 | 75 | 40 + x |
To produce more pumps more men required
∴ It is direct variation.
∴ The multiplying factor is `360/180`
More days means less employees needed.
∴ It is Indirect proportion 75
∴ The multiplying factor is `75/75`
Now 40 + x = `40 xx 360/180 xx 75/75`
40 + x = 80
x = 80 – 40
x = 40
40 more man should be employed to complete the work on time as per the agreement.
APPEARS IN
संबंधित प्रश्न
A can finish a job in 3 days whereas B finishes it in 6 days. The time taken to complete the job working together is __________ days
A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days
A alone can do a piece of work in 35 days. If B is 40% more efficient than A, then B will finish the work in ___________ days
210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?
A cement factory makes 7000 cement bags in 12 days with the help of 36 machines. How many bags can be made in 18 days using 24 machines?
A soap factory produces 9600 soaps in 6 days working 15 hours a day. In how many days will it produce 14400 soaps working 3 more hours a day?
A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?
Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?
A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together
If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?