Complete the following cost schedule :
Quantity (in Units) | 0 | 1 | 2 | 3 | 4 |
Total cost (in ₹) | 200 | ....... | ....... | ....... | ....... |
Total variable cost (in ₹) | 0 | ....... | 180 | ....... | ....... |
Average variable cost (in ₹) | ....... | 100 | ....... | 80 | ....... |
रिकाम्या जागा भरा
उत्तर
Quantity | Total Cost | Total Variable Cost | Average Variable Cost | Total Fixed Cost |
0 | 200 | 0 | - | 200 |
1 | 300 | 100 | 100 | 200 |
2 | 380 | 180 | 90 | 200 |
3 | 440 | 240 | 80 | 200 |
4 | 490 | 290 | 72.5 | 200 |