मराठी
महाराष्ट्र राज्य शिक्षण मंडळएचएससी वाणिज्य (इंग्रजी माध्यम) इयत्ता १२ वी

Fill in the blank : An assignment problem is said to be unbalanced when _______. - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Fill in the blank :

An assignment problem is said to be unbalanced when _______.

रिकाम्या जागा भरा

उत्तर

An assignment problem is said to be unbalanced when number of rows is not equal to the number of columns.

shaalaa.com
Special Cases of Assignment Problem
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 7: Assignment Problem and Sequencing - Miscellaneous Exercise 7 [पृष्ठ १२७]

APPEARS IN

बालभारती Mathematics and Statistics 2 (Commerce) [English] 12 Standard HSC Maharashtra State Board
पाठ 7 Assignment Problem and Sequencing
Miscellaneous Exercise 7 | Q 2.01 | पृष्ठ १२७

संबंधित प्रश्‍न

Four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A, B, C, D and E available. Because of limited space, machine M2 cannot be placed at C and M3 cannot be placed at A. The cost matrix is given below.

Machines Places
  A B C D E
M1 4 6 10 5 6
M2 7 4 5 4
M3 6 9 6 2
M4 9 3 7 2 3

Find the optimal assignment schedule


A company has a team of four salesmen and there are four districts where the company wants to start its business. After taking into account the capabilities of salesmen and the nature of districts, the company estimates that the profit per day in rupees for each salesman in each district is as below:

Salesman District
  1 2 3 4
A 16 10 12 11
B 12 13 15 15
C 15 15 11 14
D 13 14 14 15

Find the assignment of salesman to various districts which will yield maximum profit.


In the modification of a plant layout of a factory four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A, B, C, D and E available. Because of limited space, machine M2 cannot be placed at C and M3 cannot be placed at A. The cost of locating a machine at a place (in hundred rupees) is as follows.

Machines Location
A B C D E
M1 9 11 15 10 11
M2 12 9 10 9
M3 11 14 11 7
M4 14 8 12 7 8

Find the optimal assignment schedule.


Fill in the blank :

When the number of rows is equal to the number of columns then the problem is said to be _______ assignment problem.


Fill in the blank :

A dummy row(s) or column(s) with the cost elements as _______ is added to the matrix of an unbalanced assignment problem to convert into a square matrix.


Maximization assignment problem is transformed to minimization problem by subtracting each entry in the table from the _______ value in the table.


Fill in the blank :

In an assignment problem, a solution having _______ total cost is an optimum solution.


Fill in the blank :

In maximization type, all the elements in the matrix are subtracted from the _______ element in the matrix.


To convert the assignment problem into a maximization problem, the smallest element in the matrix is deducted from all other elements.


Solve the following problem :

The estimated sales (tons) per month in four different cities by five different managers are given below:

Manager Cities
P Q R S
I 34 36 33 35
II 33 35 31 33
III 37 39 35 35
IV 36 36 34 34
V 35 36 35 33

Find out the assignment of managers to cities in order to maximize sales.


An unbalanced assignment problems can be balanced by adding dummy rows or columns with ______ cost


For the following assignment problem minimize total man hours:

Subordinates Required hours for task
I II III IV
A 7 25 26 10
B 12 27 3 25
C 37 18 17 14
D 18 25 23 9

Subtract the `square` element of each `square` from every element of that `square`

Subordinates Required hours for task
I II III IV
A 0 18 19 3
B 9 24 0 22
C 23 4 3 0
D 9 16 14 0

Subtract the smallest element in each column from `square` of that column.

Subordinates Required hours for task
I II III IV
A `square` `square` 19 `square`
B `square` `square` 0 `square`
C `square` `square` 3 `square`
D `square` `square` 14 `square`

The lines covering all zeros is `square` to the order of matrix `square`

The assignment is made as follows:

Subordinates Required hours for task
I II III IV
A 0 14 19 3
B 9 20 0 22
C 23 0 3 0
D 9 12 14 0

Optimum solution is shown as follows:

A → `square, square` → III, C → `square, square` → IV

Minimum hours required is `square` hours


State whether the following statement is true or false:

To convert a maximization-type assignment problem into a minimization problem, the smallest element in the matrix is deducted from all elements of the matrix.


Three new machines M1, M2, M3 are to be installed in a machine shop. There are four vacant places A, B, C, D. Due to limited space, machine M2 can not be placed at B. The cost matrix (in hundred rupees) is as follows:

Machines Places
  A B C D
M1 13 10 12 11
M2 15 - 13 20
M3 5 7 10 6

Determine the optimum assignment schedule and find the minimum cost.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×