The information about numbers of workers and number of days to complete a work is given in the following table. Complete the table.

Number of workers 30 20   10  
Days 6 9 12   36
तक्‍ता पूर्ण करा
बेरीज

उत्तर

It can be observed from the given table that if the number of workers is increased from 20 to 30, then the number of days to complete the work decreases from 9 days to 6 days. So, the number of workers and the number of days to complete a work are in inverse variation.

Let the number of workers be y and the number of days to complete a work be x.

Here, y inversely varies as x, i.e., `y  α  1/z`.

\[\therefore y = \frac{k}{x}\] , where k constant of variation

⇒ x × y = k

When y = 30, x = 6.

∴ k = 6 × 30

= 180

So, the equation of variation is xy = 180.

When x = 12,

12y = 180

y = `180/12`

⇒ y = 15

When y = 10,

10x = 180

x = `180/10`

⇒ x = 18

When x = 36

36y = 180

y = `180/36`

⇒ y = 5

The complete table is given below.

Number of workers 30 20 15 10 5
Days 6 9 12 18 36
shaalaa.com
Inverse Variation
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 7: Variation - Practice Set 7.2 [पृष्ठ ३८]

APPEARS IN

बालभारती Mathematics [English] 8 Standard Maharashtra State Board
पाठ 7 Variation
Practice Set 7.2 | Q 1 | पृष्ठ ३८
बालभारती Integrated 8 Standard Part 2 [English Medium] Maharashtra State Board
पाठ 3.2 Variation
Practice Set 7.2 | Q 1. | पृष्ठ ५३
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×