Three persons can build a small house in 8 days. To build the same house in 6 days, how many persons are required?
उत्तर
Let the number of persons required to build the same house in 6 days be x.
The number of persons and the number of days required to build the house are in inverse variation. So, the product of number of persons and the number of days required to build the house is constant.
∴ x × 6 = 3 × 8
⇒ x = ` (3 xx 8) /6 = 24/6 = 4`
∴ x = 4
Thus, 4 persons are required to build the same house in 6 days.
APPEARS IN
संबंधित प्रश्न
In which of the following table x and y vary inversely:
x | 5 | 20 | 10 | 4 |
y | 20 | 5 | 10 | 25 |
In which of the following table x and y vary inversely:
x | 4 | 3 | 6 | 1 |
y | 9 | 12 | 8 | 36 |
It x and y vary inversely, fill in the following blank:
x | 16 | 32 | 8 | 128 |
y | 4 | ... | ... | 0.25 |
It x and y vary inversely, fill in the following blank:
x | 9 | ... | 81 | 243 |
y | 27 | 9 | ... | 1 |
Which of the following quantities vary inversely as other?
The number of x men hired to construct a wall and the time y taken to finish the job.
It is known that for a given mass of gas, the volume v varies inversely as the pressure p. Fill in the missing entries in the following table:
v (in cm3) | ... | 48 | 60 | ... | 100 | ... | 200 |
p (in atmospheres) | 2 | ... | 3/2 | 1 | ... | 1/2 | ... |
Which quantities in the previous question vary inversely with each other?
If x varies inversely as y and x = 4 when y = 6, then when x = 3 the value of y is ______.
If x varies inversely as y and when x = 6, y = 8, then for x = 8 the value of y is 10.
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?