Question
A contractor Abhay Singh employed some men to do a piece of work which can be done by 16 men in 14 days. At the end of 5 days, 7 of the men stopped working and 3 days later half of the remainder stopped working; the rest finished the work in 5 days. What is the number of men originally employed?
Options
25
27
29
33
MCQ
Solution
25
Explanation:
16 men can complete the work in 14 days
Let initially x men were employed
using M1D1 = M2D2
ATQ
`16xx14=5"x"+3("x"-7)+5(("x"-7))/2`
`224=(21"x"-42-35)/2`
21x = 448 + 77
`"x"=525/21=25`