Question
A takes 6 days less than B to finish a piece of work. If both A and B together can finish the work in 4 days, find the time taken by B to finish the work.
Options
12 days
`12 1/2` days
13 days
15 days
MCQ
Solution
12 days
Explanation:
Assuming that B alone takes x days to finish the work. Then A alone can finish it in (x − 6) days.
Now A’s one day’s work + B’s one day’s work = `1/"x" + 1/("x" − 6)`
and (A+B)’s one day’s work = `1/4`
`("x" - 6)/("x"("x" - 6)) + "x"/("x"("x" - 6)) = 1/4`
4(x − 6 + x) = x2 − 6x
4(2x − 6) = x2 − 6x
8x − 24 = x2 − 6x
0 = x2 − 14x + 24
0 = (x − 12) (x − 2)
x = 12 and 2
x cannot be less than 6.
So x = 12 Therefore, B also can finish the work in 12 days.