If 15 workers can build a wall in 48 hours, how many workers will be required to do the same work in 30 hours?
Sum
Solution
Let the number of workers employed to build the wall in 30 hours be y.
Number of hours | 48 | 30 |
Number of workers | 15 | y |
Obviously more the number of workers, the faster will they build the wall.
So, the number of hours and number of workers vary in inverse proportion.
So 48 × 15 = 30 × y
Therefore, `(48 xx 15)/30 = y`
y = 24
i.e., to finish the work in 30 hours, 24 workers are required.