Question
Answer the following question.
Mega Ltd. holds an Annual Management Programme every year in the month of March in which the top managerial personnel formulates plans for the next year by analyzing and predicting the future to meet future events effectively. As they are responsible for providing direction to the organization, facts are thoroughly checked using scientific calculations. Detailed plans are prepared after discussion with professional experts. Preliminary investigations are also undertaken to find out the viability of the plan. Since it is an intellectual activity requiring intelligent imagination and sound judgment so it is mainly done by the top management. Usually, rest of the members just implement the plans. Middle-level managers are neither allowed to deviate from the plans nor are they permitted to act on their own. The top management ensures that the expenses incurred in formulating the plans justify the benefits derived from them.
State any two limitations and any two features of planning discussed above.
Solution
The features of planning which are discussed in the given situation are:
- Planning is a mental exercise - "Since it is an intellectual activity requiring intelligent imagination and sound judgement so it is mainly done by top management". It requires the application of mind and sound judgement. Since planning defines what is to be done in future, it requires sound thinking rather than doing.
- Planning is futuristic - "The top management formulates plans for the next year by analyzing and predicting the future to meet future events effectively". Planning is futuristic in the sense that it foresees the future, thereby helping to prepare for uncertain future events.
Limitations:
- Planning reduces creativity - "Middle-level managers are neither allowed to deviate from the plans nor are they permitted to act on their own". Plans are made by only the top management, and the lower levels of management are not allowed to deviate from the pre-defined course. Thus, in the process, lower-level managers tend to lose their creativity.
- Planning involves huge costs - "The top management ensures that the expenses incurred in formulating the plans justify the benefits derived from them". As planning is based on future predictions, it requires much thought, analysis, scientific calculations, etc., which are to be used for formulating a course of action. This involves high costs.
RELATED QUESTIONS
Explain any three features of 'Planning.'
Give the meaning of objectives and budget as types of plans.
Define 'planning premises'.
Give the meaning of 'Strategy as a type of plan. [
If planning involves working out details for the future, why does it not ensure success?
Distinguish between method and procedure.
Who wrote the book ‘The Road to Serfdom’?
Arrange the following plans in correct chronological order
a) People’s Plan
b) Bombay Plan
c) Jawaharlal Nehru Plan
d) Vishveshwarya Plan
ITDP refers to which one of the following?
Making decisions on the basis of experience, feelings and accumulated judgement is called as ____________.
______ provides a rational approach for setting objectives and developing appropriate courses of action for achieving predetermined objectives.
Planning requires logical and systematic thinking rather than guess work. The feature of planning being referred to in the above statement is.
In how many districts, drought-prone area are identified?
What is the female literacy rate in the Bharmaur region?
Which region is popularly known as the homeland of Gaddis?
Read the following text and answer the following question on the basis of the same:
Simplex limited had been taken over by Mundhra Group immediately following India’s independence. Since then it enjoys a rich record of industry presence and experience. In 2005, with the aim to accelerate growth the company had gone through several rounds of meetings and discussions before launching ERP system to attract large projects. The management had done effective forecast and critical thinking regarding allocation resources to reduce wastage. For this purpose the company had laid down multiple courses of action to meet the challenge of adverse situations. In 2008, the company suffered loss in many projects due to the great recession despite taking many cost cutting measures. The management had taken utmost care regarding the possible outcome and timely review of the plans to achieve the set target during that hard time. In 2010 the system implemented successfully which subsequently helped the company to execute numerous projects with precision and timeliness.
“The management had taken utmost care regarding the possible outcome and timely review of the Plans to achieve the set target during that hard time.” Which is the last step of the Process mentioned here?
"lntegrated tribal development project laid the highest priority on development of transport and communications, agriculture and allied activities & social and community services" Examine the statement' in the context of Bharmaur region.
Deepti and Sudha are managers at ABC Ltd. and are working together on a project. They report to Mrs. Verma, a Senior Manager. Sudha asks Deepti to submit a report on the project to her without informing Mrs. Verma. Which Principle of Management is not followed in this case?
Planning helps in identifying deviations and taking corrective actions.