Which of the following step in the process of planning states that the manager is required to make certain assumptions about the future:

Options

  • Setting objectives

  • Developing premises

  • Evaluating alternative courses of action

  • Implementation of plan

MCQ

Solution

Developing premises

Explanation -

The term "developing premises" refers to the process of making assumptions based on previous experiences.