हिंदी

Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 3 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10
योग

उत्तर

Step 1: Row minimum

Subtract the smallest element in each row from every element in its row.

The matrix obtained is given below:

  I II III IV V
1 5 0 4 13 6
2 7 3 0 6 8
3 1 0 2 2 3
4 9 0 3 8 6
5 5 0 8 13 4

Step 2: Column minimum

Subtract the smallest element in each column of assignment matrix obtained in step 1 from every element in its column.

  I II III IV V
1 4 0 4 11 3
2 6 3 0 4 5
3 0 0 2 0 0
4 8 0 3 6 3
5 4 0 8 11 1

Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros.

First cover all rows and columns which have maximum number of zeros.

  I II III IV V
1 4 `cancel0` 4 11 3
2 `cancel6` `cancel3` `cancel0` `cancel4` `cancel5`
3 `cancel0` `cancel0` `cancel2` `cancel0` `cancel0`
4 8 `cancel0` 3 6 3
5 4 `cancel0` 8 11 1

Step 4: From step 3, minimum number of lines covering all the zeros are 3, which is less than order of matrix, i.e., 5.

∴  Select smallest element from all the uncovered elements, i.e., 1 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.

  I II III IV V
1 3 0 3 10 2
2 6 4 0 4 5
3 0 1 2 0 0
4 7 0 2 5 2
5 3 0 7 10 0

Step 5: Draw minimum number of vertical and horizontal lines to cover all zeros.

  I II III IV V
1 3 `cancel0` 3 10 2
2 `cancel6` `cancel4` `cancel0` `cancel4` `cancel5`
3 `cancel0` `cancel1` `cancel2` `cancel0` `cancel0`
4 7 `cancel0` 2 5 2
5 `cancel3` `cancel0` `cancel7` `cancel10` `cancel0`

Step 6: From step 5, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e., 5.

∴  Select smallest element from all the uncovered elements, i.e., 2 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.

  I II III IV V
1 1 0 1 8 0
2 6 6 0 4 5
3 0 3 2 0 0
4 5 0 0 3 0
5 3 2 7 10 0

Step 7: Draw minimum number of vertical and horizontal lines to cover all zeros.

  I II III IV V
1 1 `cancel0` `cancel1` 8 `cancel0`
2 6 `cancel6` `cancel0` 4 `cancel5`
3 `cancel0` `cancel3` `cancel2` `cancel0` `cancel0`
4 5 `cancel0` `cancel0` 3 `cancel0`
5 3 `cancel2` `cancel7` 10 `cancel0`

Step 8: From step 7, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e.,5.

∴ Select smallest element from all the uncovered elements, i.e., 1 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.

  I II III IV V
1 0 0 1 7 0
2 5 6 0 3 5
3 0 4 3 0 1
4 4 0 0 2 0
5 2 2 7 9 0

Step 9: Draw minimum number of vertical and horizontal lines to cover all zeros.

  I II III IV V
1 `cancel0` `cancel0` `cancel1` `cancel7` `cancel0`
2 5 6 `cancel0` 3 `cancel5`
3 `cancel0` `cancel4` `cancel3` `cancel0` `cancel1`
4 `cancel4` `cancel0` `cancel0` `cancel2` `cancel0`
5 2 2 `cancel7` 9 `cancel0`

Step 10: From step 9, minimum number of lines covering all the zeros are 5, which is equal to order of the matrix, i.e., 5.

∴ Select a row with exactly one zero, enclose that zero in ( ) and cross out all zeros in its respective column.
Similarly, examine each row and column and mark the assignment ( ).

The matrix obtained is as follows:

  I II III IV V
1 0 `cancel0` 1 7 `cancel0`
2 5 6 0 3 5
3 `cancel0` 4 3 0 1
4 4 0 `cancel0` 2 `cancel0`
5 2 2 7 9 0

Step 11: The matrix obtained in step 10 contains exactly one assignment for each row and column.

∴ Optimal assignment schedule is as follows:

Jobs Wagons Mileage
1 I 10
2 II 6
3 III 4
4 IV 9
5 V 10

∴ Total minimum mileage = 10 + 6 = 4 + 9 + 10 = 39.

shaalaa.com
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 7: Assignment Problem and Sequencing - Exercise 7.1 [पृष्ठ ११८]

APPEARS IN

बालभारती Mathematics and Statistics 2 (Commerce) [English] 12 Standard HSC Maharashtra State Board
अध्याय 7 Assignment Problem and Sequencing
Exercise 7.1 | Q 2 | पृष्ठ ११८

वीडियो ट्यूटोरियलVIEW ALL [1]

संबंधित प्रश्न

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:

         Jobs

 

 

                          Machines

P

Q

R

S

                Processing Cost (Rs.)

 

A

31

25

33

29

B

25

24

23

21

C

19

21

23

24

D

38

36

34

40

 How should the jobs be assigned to the four machines so that the total processing cost is minimum?


Solve the following minimal assignment problem and hence find the minimum value : 

  I II III IV
A 2 10 9 7
B 13 2 12 2
C 3 4 6 1
D 4 15 4 9

 


Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
                                             Service Time ( in hrs.)

Counters Salesmen
A B C D
W 41 72 39 52
X 22 29 49 65
Y 27 39 60 51
Z 45 50 48 52

Determine `l_92 and l_93, "given that"  l_91 = 97, d_91 = 38 and q_92 = 27/59`


Solve the following maximal assignment problem :

Branch Manager Monthly Business ( Rs. lakh)
A B C D
P 11 11 9 9
Q 13 16 11 10
R 12 17 13 8
S 16 14 16 12

 


A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:

Jobs Machines
(Processing Cost in ₹)
P Q R S
A 31 25 33 29
B 25 24 23 21
C 19 21 23 24
D 38 36 34 40

Find the optimal assignment to minimize the total processing cost.


Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:

Job Machines (Profit in ₹)
A B C D E
1 30 37 40 28 40
2 40 24 27 21 36
3 40 32 33 30 35
4 25 38 40 36 36
5 29 62 41 34 39

Find the optimal assignment schedule.


The assignment problem is said to be unbalance if ______


The objective of an assignment problem is to assign ______. 


Fill in the blank :

When an assignment problem has more than one solution, then it is _______ optimal solution.


Fill in the blank :

An _______ is a special type of linear programming problem.


In an assignment problem, if number of column is greater than number of rows, then a dummy column is added.


Solve the following problem :

A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.

  I II III IV
A 7 25 26 10
B 12 27 3 25
C 37 18 17 14
D 18 25 23 9

How should the tasks be allocated, one to a man, as to minimize the total man hours?


Choose the correct alternative:

The assignment problem is generally defined as a problem of ______


Choose the correct alternative: 

Assignment Problem is special case of ______


Choose the correct alternative:

When an assignment problem has more than one solution, then it is ______


Choose the correct alternative:

The assignment problem is said to be balanced if ______


If the given matrix is ______ matrix, the assignment problem is called balanced problem


In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added


State whether the following statement is True or False:

In assignment problem, if number of columns is greater than number of rows, then a dummy row is added


State whether the following statement is True or False: 

In assignment problem each worker or machine is assigned only one job


Give mathematical form of Assignment problem


What is the difference between Assignment Problem and Transportation Problem?


Three jobs A, B and C one to be assigned to three machines U, V and W. The processing cost for each job machine combination is shown in the matrix given below. Determine the allocation that minimizes the overall processing cost.

    Machine
    U V W
Jobs A 17 25 31
B 10 25 16
C 12 14 11

(cost is in ₹ per unit)


A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:

    Tasks
    1 2 3 4
Subordinates P 8 26 17 11
  Q 13 28 4 26
  R 38 19 18 15
  S 9 26 24 10

How should the tasks be allocated to subordinates so as to minimize the total manhours?


Find the optimal solution for the assignment problem with the following cost matrix.

    Area
    1 2 3 4
  P 11 17 8 16
Salesman Q 9 7 12 6
  R 13 16 15 12
  S 14 10 12 11

Choose the correct alternative:

Number of basic allocation in any row or column in an assignment problem can be


Choose the correct alternative:

North – West Corner refers to ______


Choose the correct alternative:

The solution for an assignment problem is optimal if


Choose the correct alternative:

In an assignment problem involving four workers and three jobs, total number of assignments possible are


A car hire company has one car at each of five depots a, b, c, d and e. A customer in each of the fine towers A, B, C, D and E requires a car. The distance (in miles) between the depots (origins) and the towers(destinations) where the customers are given in the following distance matrix.

  a b c d e
A 160 130 175 190 200
B 135 120 130 160 175
C 140 110 155 170 185
D 50 50 80 80 110
E 55 35 70 80 105

How should the cars be assigned to the customers so as to minimize the distance travelled?


A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.

  I II III IV V
A 150 120 175 180 200
B 125 110 120 150 165
C 130 100 145 160 170
D 40 40 70 70 100
E 45 25 60 70 95

How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?


A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:

Job Machines
(Processing cost in ₹)
I II III IV
P 31 25 33 29
Q 25 24 23 21
R 19 21 23 24
S 38 36 34 40

Find the optimal assignment to minimize the total processing cost.


A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?

Workers Packing of
  Books Toys Crockery Cutlery
A 3 11 10 8
B 13 2 12 12
C 3 4 6 1
D 4 15 4 9

Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 7 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10

A job production unit has four jobs P, Q, R, S which can be manufactured on each of the four machines I, II, III and IV. The processing cost of each job for each machine is given in the following table :

Job Machines
(Processing cost in ₹)
I II III IV
P 31 25 33 29
Q 25 24 23 21
R 19 21 23 24
S 38 36 34 40

Complete the following activity to find the optimal assignment to minimize the total processing cost.

Solution:

Step 1: Subtract the smallest element in each row from every element of it. New assignment matrix is obtained as follows :

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 2: Subtract the smallest element in each column from every element of it. New assignment matrix is obtained as above, because each column in it contains one zero.

Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros:

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 4: From step 3, as the minimum number of straight lines required to cover all zeros in the assignment matrix equals the number of rows/columns. Optimal solution has reached.

Examine the rows one by one starting with the first row with exactly one zero is found. Mark the zero by enclosing it in (`square`), indicating assignment of the job. Cross all the zeros in the same column. This step is shown in the following table :

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 5: It is observed that all the zeros are assigned and each row and each column contains exactly one assignment. Hence, the optimal (minimum) assignment schedule is :

Job Machine Min.cost
P II `square`
Q `square` 21
R I `square`
S III 34

Hence, total (minimum) processing cost = 25 + 21 + 19 + 34 = ₹`square`


A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:

  I II III IV
A 3 11 10 8
B 13 2 12 2
C 3 4 6 1
D 4 15 4 9

Complete the following activity to allocate tasks to subordinates to minimize total time.

Solution:

Step I: Subtract the smallest element of each row from every element of that row:

  I II III IV
A 0 8 7 5
B 11 0 10 0
C 2 3 5 0
D 0 11 0 5

Step II: Since all column minimums are zero, no need to subtract anything from columns.

Step III: Draw the minimum number of lines to cover all zeros.

  I II III IV
A 0 8 7 5
B 11 0 10 0
C 2 3 5 0
D 0 11 0 5

Since minimum number of lines = order of matrix, optimal solution has been reached

Optimal assignment is A →`square`  B →`square`

C →IV  D →`square`

Total minimum time = `square` hours.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×