P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
उत्तर
P can do a piece of work in 12 days.
∴ P’s 1 day work = `1/12`
P’s 3 day’s work = `3 xx 1/12 = 3/12`
Q can do a piece of work in 15 days.
∴ Q’s 1 day work = `1/15`
Remaining work after 3 days = `1 - 3/12 = 9/12`
(P + Q)'s 1 day work = `1/2 + 1/15`
= `5/60 + 4/60`
= `9/60`
∴ Number of days required to finish the remaining work 9
= `"Remaining work"/(("P" + "Q")"'s" 1 "day work")`
= `(9/12)/(9/60)`
= `9/12 xx 60/9`
= 5
Remaining work lasts for 5 days
Total work lasts for 3 + 5 = 8 days.
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?