प्रश्न
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
उत्तर
3 men = 6 boys
4 men = `6/3xx4` = 8
Total boys in second case :
= 4 men + 12 boys = 8 + 12 = 20 boys
6 boys can do a piece of work in 20 days
Then let 20 boys will do the same work in x days
∴ 6 : 20 : : 20 : x ........(More boys,less days)
⇒ 6 : 20 : : x : 20 ....(By inverse proportion)
x = `(20xx6)/20`
= 6 days
∴ They will do the work in 6 days
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?