प्रश्न
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
उत्तर
A can finish a piece of work in = 15 days
B can finish a piece of work in = 10 days
∴ A's 1 day work =`1/15`
B's 1-day work =`1/10`
(A+B)'s 1-day work =`1/15+1/10`
`=(2+3)/30=5/30=1/6`
(A+B)'s 2 days work =`1/6xx2=1/3`
Remaining work which will be done by A alone
`=1-1/3=(3-1)/3=2/3`
∴ A can finish 1 work in = 15 days
A can finish `2/3` work in =`15xx2/3` days
`=30/3`days = 10 days
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.