प्रश्न

A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?

योग

उत्तर

A's 1-day work = `1/15`

B's 1-day work = `1/20`

(A+B)'s 1-day work =`1/15+1/20`

`=(4+3)/60=7/60`

(A+B)'s 4 days work =`7/60xx4=7/15`

Remaining work =`1-7/15=(15-7)/15`

`=8/15`

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (E) | Q 3 | पृष्ठ १३३

संबंधित प्रश्न

A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?


12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.


If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×