A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
उत्तर
A can do a piece of work in = 6 days
B can do a piece of work in = 12 days
C can do a piece of work in = 24 days
∴ A's 1-day work =`1/6`
∴ B's 1-day work = `1/12`
∴ C's 1-day work = `1/24`
(A+B+C)'s 1-day work =`1/6+1/12+1/24`
`=(4+2+1)/24=7/24`
∴ (A+B+C) can do the work in =`24/7` days
`=3 3/7` days
APPEARS IN
संबंधित प्रश्न
A train is moving with a uniform speed of 120 km per hour.
(i) How far will it travel in 36 minutes?
(ii) In how much time will it cover 210 km?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?