A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?

बेरीज

उत्तर

A's 1-day work = `1/15`

B's 1-day work = `1/20`

(A+B)'s 1-day work =`1/15+1/20`

`=(4+3)/60=7/60`

(A+B)'s 4 days work =`7/60xx4=7/15`

Remaining work =`1-7/15=(15-7)/15`

`=8/15`

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (E) | Q 3 | पृष्ठ १३३

संबंधित प्रश्‍न

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?


A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?


A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×