प्रश्न
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
उत्तर
A's 1-day work = `1/15`
B's 1-day work = `1/20`
(A+B)'s 1-day work =`1/15+1/20`
`=(4+3)/60=7/60`
(A+B)'s 4 days work =`7/60xx4=7/15`
Remaining work =`1-7/15=(15-7)/15`
`=8/15`
APPEARS IN
संबंधित प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?