प्रश्न
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?
उत्तर
X can do the work in 6 days.
X’s 1 day work = `1/6`
X’s share for 1 day = `1/6 xx 48000` = ₹ 8000
X’s share for 3 days = 3 × 8000 = ₹ 24000
Y can complete the work in 8 days.
Y’s 1 day work = `1/8`
Y’s 1 day share = `1/8 xx 48000` = ₹ 6000
Y’s 3 days share = ₹ 6000 × 3 = ₹ 18000
(X + Y)’s 3 days share = ₹ 24000 + ₹ 18000 = ₹ 42000
Remaining money is Z’s share
∴ Z’s share = ₹ 48000 – ₹ 42000 = ₹ 6000
APPEARS IN
संबंधित प्रश्न
22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day?
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.