A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
उत्तर
A and B can do a work in = 8 days
B and C can do a work in = 12 days
A and C can do a work in = 16 days
(A+B)’s 1-day work =`1/8`
(B+C)’s 1-day work =`1/12`
(A+C)'s 1-day work =`1/16`
∴ [(A+B)+(B+C)+(A+C)]'s 1 day work
`=1/8+1/12+1/16`
i.e. [A+B+B+C+A+C]'s 1 day work
`=1/8+1/12+1/16`
`=(6+4+3)/48=13/48`
i.e. 2(A+B+C)'s 1-day work =`13/48`
i.e. (A+B+C)'s 1-day work =`13/48xx1/2=13/96`
∴ (A+B+C) can do the work in =`96/13`days
`=7 5/13` days
APPEARS IN
संबंधित प्रश्न
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?