प्रश्न

A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?

योग

उत्तर

A and B can do a work in = 8 days

B and C can do a work in = 12 days

A and C can do a work in = 16 days

(A+B)’s 1-day work =`1/8`

(B+C)’s 1-day work =`1/12`

(A+C)'s 1-day work =`1/16`

∴ [(A+B)+(B+C)+(A+C)]'s 1 day work

`=1/8+1/12+1/16`

i.e. [A+B+B+C+A+C]'s 1 day work

`=1/8+1/12+1/16`

`=(6+4+3)/48=13/48`

i.e. 2(A+B+C)'s 1-day work =`13/48`

i.e. (A+B+C)'s 1-day work =`13/48xx1/2=13/96`

∴ (A+B+C) can do the work in =`96/13`days

`=7 5/13` days

shaalaa.com
Time and Work
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
अध्याय 10 Direct and Inverse Variations
Exercise 10 (E) | Q 12 | पृष्ठ १३३

संबंधित प्रश्न

A car takes 6 hours to reach a destination by travelling at a speed of 50 km per hour. How long will it take when the car travels at a speed of 75 km per hour?


If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?


If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?


A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?


A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×