A Can Do a Piece of Work in 10 Days and B in 15 Days. How Long Will They Take Together to Finish It? - Mathematics

Advertisements
Advertisements

प्रश्न

A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?

बेरीज

उत्तर

A's 1-day work =`1/10`

B's 1-day work =`1/15`

(A + B)'s 1-day work =`1/10+1/15`

`=(3+2)/30=5/30`

`=1/6`

∴ Both A and B together can finish the work in = 6 days

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (E) | Q 1 | पृष्ठ १३३

संबंधित प्रश्‍न

Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.


If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?


90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?


Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?


A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?


A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×