A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
उत्तर
A's 1-day work =`1/10`
B's 1-day work =`1/15`
(A + B)'s 1-day work =`1/10+1/15`
`=(3+2)/30=5/30`
`=1/6`
∴ Both A and B together can finish the work in = 6 days
APPEARS IN
संबंधित प्रश्न
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working `7 1/2` hours a day?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?