A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
उत्तर
A's one day's work =`1/10`
B's one day's work =`1/12`
C's one day's work =`1/15`
A, B and C's one day's work =`1/10+1/12+1/15`
`=(6+5+4)/60=15/60=1/4`
Let the work completed in x days
∴ A's 2 days work + B's (x − 3) days work + C's x days work = 1
`⇒2xx1/10+("x"-3)xx1/12+"x"xx1/15=1`
`⇒1/5+("x"-3)/12+"x"/15=1`
`(12+5"x"-15+4"x"=60)/60` ...(L.C.M of 5, 12, 15 = 60)
⇒ 9x = 60 − 12 + 15
⇒ 9x = 63
`⇒"x"=63/9=7`
∴ Work will last for 7 days
APPEARS IN
संबंधित प्रश्न
In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
If 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?
Twelve typists, all working with the same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?
X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?