A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
उत्तर
A and B can do a piece of work in = 40 days
B and C can do a piece of work in = 30 days
C and A can do a piece of work in = 24 days
(A+B)’s 1-day work =`1/40`
(B+C)’s 1-day work =`1/30`
(C+A)’s 1-day work =`1/24`
(i) [(A+B)+(B+C)+(C+A)]’s 1 day work = `1/40+1/30+1/24`
`=(3+4+5)/120`
`=12/120=1/10`
i.e. (A+B+B+C+C+A)'s 1-day work =`1/10`
i.e. 2 (A+B+C)'s 1-day work =`1/10`
∴ (A+B+C)'s 1-day work =`1/10xx1/2`
`=1/20`
∴ (A+B+C) can do the work in = 20 days
(ii) A's 1-day work =`1/20-1/30`
`=(3-2)/60=1/60`
∴ A can do the work in 60 days
B's 1-day work =`1/20-1/24`
`=(6-5)/120=1/120`
∴ B can do the work in 120 days
now, C's 1-day work =`1/20-1/40`
`=(2-1)/40=1/40`
C can do the work in 40 days
Hence A can do the work in = 60 days
B can do the work in = 120 days
C can do the work in = 40 days
APPEARS IN
संबंधित प्रश्न
12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?
If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?
A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.