प्रश्न
A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
- How long will it take them to do the work together?
- In what time can each finish it working alone?
उत्तर
A and B can do a piece of work in = 40 days
B and C can do a piece of work in = 30 days
C and A can do a piece of work in = 24 days
(A+B)’s 1-day work =`1/40`
(B+C)’s 1-day work =`1/30`
(C+A)’s 1-day work =`1/24`
(i) [(A+B)+(B+C)+(C+A)]’s 1 day work = `1/40+1/30+1/24`
`=(3+4+5)/120`
`=12/120=1/10`
i.e. (A+B+B+C+C+A)'s 1-day work =`1/10`
i.e. 2 (A+B+C)'s 1-day work =`1/10`
∴ (A+B+C)'s 1-day work =`1/10xx1/2`
`=1/20`
∴ (A+B+C) can do the work in = 20 days
(ii) A's 1-day work =`1/20-1/30`
`=(3-2)/60=1/60`
∴ A can do the work in 60 days
B's 1-day work =`1/20-1/24`
`=(6-5)/120=1/120`
∴ B can do the work in 120 days
now, C's 1-day work =`1/20-1/40`
`=(2-1)/40=1/40`
C can do the work in 40 days
Hence A can do the work in = 60 days
B can do the work in = 120 days
C can do the work in = 40 days
APPEARS IN
संबंधित प्रश्न
In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
A garrison has sufficient provisions for 480 men for 12 days. If the number of men is reduced by 160; find how long will the provisions last?
If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.
P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?