A Can Do a Piece of Work in 20 Days and B in 15 Days. They Worked Together on It for 6 Days and Then a Left. How Long Will B Take to Finish the Remaining Work? - Mathematics

Advertisements
Advertisements

प्रश्न

A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?

बेरीज

उत्तर

Given,

A can do a piece of work in = 20 days

B can do a piece of work in = 15 days

∴ A's 1-day work =`1/20`

B's 1-day work = `1/15`

(A+B)'s 1-day work =`1/20+1/15`

`=(3+4)/60=7/60`

(A+B)'s 6 days work =`7/60xx6=7/10`

Remaining work =`1-7/10`

`=(10-7)/10=3/10`

B can do 1 work in = 15 days

B can do `3/10` work in =`15xx3/10` days

`=45/10`days =`9/2` days = `4 1/2` days

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (E) | Q 7 | पृष्ठ १३३
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×