प्रश्न
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days?
उत्तर
Men: Days:: Men: Days
36 : 7 :: x : 42
∴ By inverse proportional
36 × 7 = x × 42
`⇒"x"=(36xx7)/42`
= 6 men
APPEARS IN
संबंधित प्रश्न
72 men do a piece of work in 25 days. In how many days will 30 men do the same work?
Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.
If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?
A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?
A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?
A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3` days. In how many days can A and C do it working together?
A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?
A can-do `1/4` of work in 5 days and B can do `1/3` of the same work in 10 days. Find the number of days in which both working together will complete the work.
A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?
Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.