प्रश्न

A can do a piece of work in 24 days, A and B can do it in 16 days and A, B, and C in `10 2/3`  days. In how many days can A and C do it working together?

बेरीज

उत्तर

A can do a piece of work in = 24 days

(A+B) can do a piece of work in = 16 days

(A+B+C) can do a piece of work in

`=10 2/3`days = `32/3` days

∴ A's 1-day work =`1/24`

(A+B)'s 1 day work =`1/16`

(A+B+C)'s 1 day work =`3/32`

C's 1 day work =`3/32-1/16`

`=(3-2)/32=1/32`

(A+C)'s 1-day work =`1/24+1/32`

`=(4+3)/96=7/96`

∴ (A+C) can do the work in =`96/7` days

`=13 5/7` days

shaalaa.com
Time and Work
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Direct and Inverse Variations - Exercise 10 (E) [पृष्ठ १३३]

APPEARS IN

सेलिना Concise Mathematics [English] Class 8 ICSE
पाठ 10 Direct and Inverse Variations
Exercise 10 (E) | Q 6 | पृष्ठ १३३

संबंधित प्रश्‍न

12 pipes, all of the same size, fill a tank in 42 minutes. How long will it take to fill the same tank, if 21 pipes of the same size are used?


72 men do a piece of work in 25 days. In how many days will 30 men do the same work?


If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?


Cost of 24 identical articles is Rs. 108, Find the cost of 40 similar articles.


If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


A can do a piece of work in 10 days, B in 12 days, and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×