X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share? - Mathematics

Advertisements
Advertisements

Question

X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?

Sum

Solution

X can do the work in 6 days.

X’s 1 day work = `1/6`

X’s share for 1 day = `1/6 xx 48000` = ₹ 8000

X’s share for 3 days = 3 × 8000 = ₹ 24000

Y can complete the work in 8 days.

Y’s 1 day work = `1/8`

Y’s 1 day share = `1/8 xx 48000` = ₹ 6000

Y’s 3 days share = ₹ 6000 × 3 = ₹ 18000

(X + Y)’s 3 days share = ₹ 24000 + ₹ 18000 = ₹ 42000

Remaining money is Z’s share

∴ Z’s share = ₹ 48000 – ₹ 42000 = ₹ 6000

shaalaa.com
Time and Work
  Is there an error in this question or solution?
Chapter 4: Life Mathematics - Exercise 4.5 [Page 152]

APPEARS IN

Samacheer Kalvi Mathematics [English] Class 8 TN Board
Chapter 4 Life Mathematics
Exercise 4.5 | Q 15 | Page 152

RELATED QUESTIONS

If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?


In order to complete a work in 28 days, 60 men are required. How many men will be required if the same work is to be completed in 40 days?


A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 more soldiers come to the fort. Find in how many days will the remaining provisions last at the same rate?


A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?


A, B, and C can do a piece of work in 6 days, 12 days, and 24 days respectively. In what time will they altogether do it?


A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work?


A can do a piece of work in 10 days; B in 18 days; and A, B, and C together in 4 days. In what time would C alone do it?


A and B can do a work in 8 days; B and C in 12 days, and A and C in 16 days. In what time could they do it, all working together?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.