Raghuram has been appointed as the stock incharge in a readymade shirt manufacturing company. The Production Manager asks Raghuram to ensure the availability of fabric without any interruption so - Entrepreneurship

Advertisements
Advertisements

प्रश्न

Raghuram has been appointed as the stock incharge in a readymade shirt manufacturing company. The Production Manager asks Raghuram to ensure the availability of fabric without any interruption so that there is no stock-out situation. For this Raghuram wants to know the re-order point of fabric for the company, that is to determine when to place an order. For this he found out the procurement lead time, which is 2 months, and the demand during this period, which is expected to be 300 bales of cotton fabric per month. So the order should be placed when the stock reaches:

विकल्प

  • 600 bales

  • 450 bales

  • 300 bales

  • 150 bales

MCQ

उत्तर

600 bales

Explanation:

Re-order point = Lead time × Demand per month

Given:

Lead time = 2 months
Demand per month = 300 bales

Re-order point = 2 × 300

= 600 bales