Question
Raghuram has been appointed as the stock incharge in a readymade shirt manufacturing company. The Production Manager asks Raghuram to ensure the availability of fabric without any interruption so that there is no stock-out situation. For this Raghuram wants to know the re-order point of fabric for the company, that is to determine when to place an order. For this he found out the procurement lead time, which is 2 months, and the demand during this period, which is expected to be 300 bales of cotton fabric per month. So the order should be placed when the stock reaches:
Options
600 bales
450 bales
300 bales
150 bales
Solution
600 bales
Explanation:
Re-order point = Lead time × Demand per month
Given:
Lead time = 2 months
Demand per month = 300 bales
Re-order point = 2 × 300
= 600 bales