प्रश्न
______ time is the time when the machine is available but is waiting for a job to be processed
उत्तर
Idle
APPEARS IN
संबंधित प्रश्न
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
Job | I | II | IIII | IV | V | VI | VII |
Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
Jobs | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Fill in the blank :
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______
One machine - one job is not an assumption in solving sequencing problems.
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
Type | 1 | 2 | 3 | 4 | 5 |
Machine A | 16 | 20 | 12 | 14 | 22 |
Machine B | 10 | 12 | 4 | 6 | 8 |
Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
In assignment problem each worker or machine is ______ capable of handling any job
State whether the following statement is True or False:
One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______