प्रश्न
______ time is the time when the machine is available but is waiting for a job to be processed
उत्तर
Idle
APPEARS IN
संबंधित प्रश्न
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
Policy | 1 | 2 | 3 |
Data Entry | 90 | 120 | 180 |
Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
Jobs | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Choose the correct alternative :
The objective of sequencing problem is
One machine - one job is not an assumption in solving sequencing problems.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
State whether the following is True or False :
The time involved in moving a job from one machine to another is negligibly small.
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
Machines | Jobs (Processing times in minutes) | ||||||
I | II | III | IV | V | VI | VII | |
Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
Solve the following problem :
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.
Job | Shaping (Minutes) | Drilling (Minutes) | Trapping (Minutes) |
1 | 13 | 3 | 18 |
2 | 18 | 8 | 4 |
3 | 8 | 6 | 13 |
4 | 23 | 6 | 8 |
Choose the correct alternative:
Machine | Job | |||
A | B | C | D | |
I | 5 | 6 | 8 | 4 |
II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type