Advertisements
Advertisements
प्रश्न
State whether the following is True or False :
The time involved in moving a job from one machine to another is negligibly small.
विकल्प
True
False
उत्तर
The time involved in moving a job from one machine to another is negligibly small True.
APPEARS IN
संबंधित प्रश्न
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department
Job | I | II | III |
Department A | 8 | 6 | 5 |
Department B | 8 | 3 | 4 |
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
Policy | 1 | 2 | 3 |
Data Entry | 90 | 120 | 180 |
Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Choose the correct alternative :
In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
Fill in the blank :
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
In assignment problem each worker or machine is ______ capable of handling any job
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
Book | I | II | III | IV | V |
Machine A | 4 | 9 | 8 | 6 | 5 |
Machine B | 5 | 6 | 2 | 3 | 4 |
Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.