Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
उत्तर
The time for which a machine j does not have a job to process to the start of job is called Idle time.
APPEARS IN
संबंधित प्रश्न
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
Policy | 1 | 2 | 3 |
Data Entry | 90 | 120 | 180 |
Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
Job | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
Jobs | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Fill in the blank :
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______
One machine - one job is not an assumption in solving sequencing problems.
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
Machines | Jobs (Processing times in minutes) | ||||||
I | II | III | IV | V | VI | VII | |
Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
Choose the correct alternative:
Machine | Job | |||
A | B | C | D | |
I | 5 | 6 | 8 | 4 |
II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
State whether the following statement is True or False:
In sequencing problem each machine is of different type
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______