हिंदी

Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hrs. - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.

Jobs I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7

Find the appropriate regression equation and use it to estimate the blood pressure of a woman with age 47 years. Find the optimal sequence that minimizes total time required to complete the following jobs in order A-B-C. The processing times are given in hrs.

Job I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7
सारिणी
योग

उत्तर

Job I II III IV V VI VII
Machine A 6 7 5 11 6 7 12
Machine B 4 3 2 5 1 5 3
Machine C 3 8 7 4 9 8 7

Here min A = 5, max B = 5, min C = 3

Since min A ≥ max B is satisfied, the problem can be converted into a two machine problem.

Let G and H be two fictitious machines such that G = A + B and H = B + C

Then the problem can be written as

Job I II III IV V VI VII
Machine G 10 10 7 16 7 12 15
Machine H 7 11 9 9 10 13 10

Observe that Min (G, H) = 7, corresponds to job I on machine H, job III on machine G and job V on machine G.

∴ Job I is placed last in sequence, Job III and V are placed either first or second in sequence.

V III         I
OR
III V         I

Then the problem reduces to

Job II IV VI VII
Machine G 10 16 12 15
Machine H 11 9 13 10

Now, Min (G, H) = 9, corresponds to Job IV on machine H.

∴ Job IV is placed second last in the sequence.

V III       IV I
OR
III V       IV I

Then the problem reduces to

Job II VI VII
Machine G 10 12 15
Machine H 11 13 10

Now, Min (G, H) = 10, corresponds to Job II on machine G and Job VII on machine H.

∴  Job II is placed third in the sequence, Job VII is placed third last in the sequence and remaining Job VI is placed fourth in the sequence.

V III II VI VII IV I
OR
III V II VI VII IV I

∴ We consider the optimal sequence as V – III – II – VI – VII – IV – I

Total elapsed time

Job Machine
A
Machine
B
Machine
C
In Out In  Out In  Out
V (6, 1, 9) 0 6 6 7 7 16
III (5, 2, 7) 6 11 11 13 16 23
II (7, 3, 8) 11 18 18 21 23 31
VI (7, 5, 8) 18 25 25 30 31 39
VII (12, 3, 7) 25 37 37 40 40 47
IV (11, 5, 4) 37 48 48 53 53 57
I (6, 4, 3) 48 54 54 58 58 61

Total elapsed time = 61 hrs

Idle time for Machine A = 61 –  54 = 7 hrs

Idle time for Machine B = (61 – 58) + 6 + 4 + 5 + 4 + 7 + 8 + 1 = 38 hrs

Idle time for Machine C = 7 + 1 + 6 + 1 = 15 hrs.

shaalaa.com
Types of Sequencing Problem
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 7: Assignment Problem and Sequencing - Exercise 7.2 [पृष्ठ १२५]

संबंधित प्रश्न

A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.

Job 1 2 3 4 5 6
Time of turning 3 12 5 2 9 11
Time for threading 8 10 9 6 3 1

A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department

Job I II III
Department A 8 6 5
Department B 8 3 4

Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.


An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:

Policy 1 2 3
Data Entry 90 120 180
Filing 140 110 100

Find the sequence that minimizes the total time required to complete the entire task.


Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II IIII IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

Choose the correct alternative :

The objective of sequencing problem is


If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.


Fill in the blank :

The time for which a machine j does not have a job to process to the start of job is called _______.


Fill in the blank :

The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______


State whether the following is True or False :

If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.


State whether the following is True or False :

In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.


State whether the following is True or False :

The time involved in moving a job from one machine to another is negligibly small.


Solve the following problem :

A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:

Items 1 2 3 4 5 6 7
Time for Cutting 5 7 3 4 6 7 12
Time for Sewing 2 6 7 5 9 5 8

Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.


A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.

Type 1 2 3 4 5
Machine A 16 20 12 14 22
Machine B 10 12 4 6 8
Machine C 8 18 16 12 10

Solve the problem for minimizing the total elapsed time.


If there are n jobs and m machines, then there will be _______ sequence of doing jobs.


Choose the correct alternative:

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


______ time is the time when the machine is available but is waiting for a job to be processed


In sequencing problem the time required to transfer a job from one machine to another is ______


State whether the following statement is True or False: 

One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine


State whether the following statement is True or False:

The Total Elapsed is the time required to complete all the jobs i.e. entire task


State whether the following statement is True or False:

The idle time for a machine is the when machine is available but is not waiting for any job to be processed


State whether the following statement is True or False: 

In sequencing problem each job once started on any machine must be processed still its completion


State whether the following statement is True or False:

In sequencing problem each machine is of different type


The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×