Advertisements
Advertisements
प्रश्न
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
विकल्प
True
False
उत्तर
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines False.
APPEARS IN
संबंधित प्रश्न
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
Fill in the blank :
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
Machines | Jobs (Processing times in minutes) | ||||||
I | II | III | IV | V | VI | VII | |
Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
Type | 1 | 2 | 3 | 4 | 5 |
Machine A | 16 | 20 | 12 | 14 | 22 |
Machine B | 10 | 12 | 4 | 6 | 8 |
Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
Solve the following problem :
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.
Job | Shaping (Minutes) | Drilling (Minutes) | Trapping (Minutes) |
1 | 13 | 3 | 18 |
2 | 18 | 8 | 4 |
3 | 8 | 6 | 13 |
4 | 23 | 6 | 8 |
Choose the correct alternative:
Machine | Job | |||
A | B | C | D | |
I | 5 | 6 | 8 | 4 |
II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.
Jobs | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
Book | I | II | III | IV | V |
Machine A | 4 | 9 | 8 | 6 | 5 |
Machine B | 5 | 6 | 2 | 3 | 4 |
Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.